By Tony Capaccio (Bloomberg) The Navy’s new Virginia-class submarines are projected to run $17 billion over their planned budget through 2030, a problem emblematic of a crisis in the program, the House’s top lawmaker on defense spending disclosed.
“It’s clear that the Navy and shipbuilders have known about this shortfall for at least 18 months” but “Congress was notified just two weeks ago,” Representative Ken Calvert, chairman of the House defense appropriations subcommittee, said in remarks released Thursday before a classified hearing with Navy Secretary Carlos Del Toro.
The program for a new generation of nuclear-powered subs being manufactured by General Dynamics Corp. and HII “has slipped two to three years” behind schedule “and is experiencing extraordinary cost growth,” Calvert said. The $17 billion shortfall will increase the program’s projected $184 billion total cost if the Navy can’t close the gap by finding ways to cut expenditures.
Several Navy ship programs, including the Virginia class, “are in crisis,” he said. Calvert, a California Republican and usually an enthusiastic supporter of defense programs, lambasted the Navy for what he called a lack of candor in disclosing problems and for poor metrics in overseeing multibillion-dollar programs.
“It’s not clear to me that anyone has accurate information about the trajectory of any shipbuilding program other than the program executive officers — and since they switch out every two years, the options for long-term accountability are limited,” Calvert said. “For too long, this committee has been put in a position of asking what the Navy is hiding behind the curtain. It’s time to pull down the curtain altogether,” he said.
The Navy said in a statement after the hearing that Del Toro “has been advocating for improvements to the maritime industrial base, and to increase funding to ensure the Navy meets its acquisition objectives.”
To demonstrate fiscal responsibility, the Navy has set up “an independent Naval Cost Agency to improve cost estimations and created a Maritime Industrial Base program to manage the funding supporting the industrial base,” according to the statement. The Navy said it’s working to improve ship design processes and investing in modern facilities.
General Dynamics did not immediately respond to requests for comment made after normal business hours on Thursday. A representative for HII said the company would comment before House members on Friday.
The Virginia-class submarine is armed with both torpedoes and land-attack missiles and, starting later this year, with anti-ship Tomahawk cruise missiles. The vessels are intended to give the US a crucial advantage in any conflict with China.
Aukus Risk
Overall, delivery dates for Virginia-class subs are running an estimated 24 to 36 months past the contracted dates, according to the Navy’s 45-day ship review released in April. General Dynamics and HII are supposed to be completing two submarines a year but instead are averaging the completion of one plus 20% of the work building a second sub. The Navy projects the contractors won’t hit the two-a-year rate by 2028.
The Virginia-class delays could undermine the Aukus partnership involving the US, Australia and the UK if they aren’t reversed soon.
Under the Aukus agreement, starting in about 2032 the US Navy is supposed to sell Australia the first of as many as five existing or new Virginia-class subs. Those vessels would fill a gap until delivery in the late 2030s of the first new vessels to be built in the UK and Australia with technology from the US and UK.
SEOUL, Oct 26 (Reuters) – South Korea’s HD Hyundai Heavy Industries 329180.KS and U.S. military shipbuilder Huntington Ingalls HII.N have agreed to jointly build U.S. navy auxiliary ships, the South Korean shipbuilder said on Sunday. In a bid...
Classification society DNV has awarded HD Korea Shipbuilding & Offshore Engineering an Approval in Principle for a 15,000 TEU container vessel design powered by nuclear-powered Small Modular Reactor technology. The...
Belgian offshore wind contractor DEME has taken delivery of its new wind turbine installation vessel Norse Wind at the CIMC Raffles Shipyard. The vessel is designed to install the next...
October 22, 2025
Total Views: 1572
Get The Industry’s Go-To News
Subscribe to gCaptain Daily and stay informed with the latest global maritime and offshore news
— just like 107,163 professionals
Secure Your Spot
on the gCaptain Crew
Stay informed with the latest maritime and offshore news, delivered daily straight to your inbox
— trusted by our 107,163 members
Your Gateway to the Maritime World!
Essential news coupled with the finest maritime content sourced from across the globe.