Six Years Late And $2.8 Billion Over Budget Navy’s Costly Carrier Is Ready For Training And Operations

The USS Gerald R. Ford (CVN 78). The first-of-class ship -- the first new U.S. aircraft carrier design in 40 years. (U.S. Navy Combat Camera photo by Mass Communication Specialist 2nd Class Ridge Leoni/Released)

Six Years Late And $2.8 Billion Over Budget Navy’s Costly Carrier Is Ready For Training And Operations

Bloomberg
Total Views: 14193
January 2, 2022

By Tony Capaccio (Bloomberg) –The Navy’s costliest warship finally has all the elevators needed to lift bombs from below its deck so it can deploy on its first operational patrol — more than four and a half years after delivery.

The service has announced that the 11th and final Advanced Weapons Elevator is in place on the $13.3 billion USS Gerald R. Ford and the aircraft carrier is ready for training and operations.

“This is a significant milestone for the Navy, ship and her crew,” Rear Admiral James Downey, the Navy’s program executive officer for aircraft carriers, said in a statement.  “We now have the entire system to operate and train with.” He said the service and the prime contractor, Huntington Ingalls Industries Inc., used “hundreds of craftsmen, technicians and engineers, working around the clock –through multiple underway and holiday periods — to get these advanced systems on line and operational.”

The Navy took delivery of the first in the Ford class of carriers in May 2017, praising the “newest, most capable, most advanced warship” and saying it was “expected to be operational in 2020.” The service didn’t disclose that none of the 11 elevators were operational, much less installed, until Bloomberg News reported the problem in November 2018.

“I recognize the extraordinary effort that it has taken to finish all 11 of these elevators, but this effort should not have been necessary,” Senator James Inhofe of Oklahoma, the top Republican on the Senate Armed Services Committee and the most vocal congressional critic of the Navy on the issue, said in a statement.

The carrier ultimately was delivered “six years late and $2.8 billion over budget,” Inhofe said.

Related Article: U.S. Navy’s New Supercarrier Completes Explosive Shock Trials

The delay to fix the elevators and resolve other issues “has lengthened a period during which the Navy is attempting to maintain policy maker-desired levels of carrier forward deployments with its 10 other carriers,” the nonpartisan Congressional Research Service said in a report this month.

Inhofe put it more bluntly. He said the delay has forced other ships and crews to deploy “longer and more often,” as well as causing gaps in the Navy’s global “presence when no carrier could deploy, at a time when naval presence and capability could not be more critical for our national security.”

Perhaps the only positive outcome of the weapons elevator delays is “development of what the Navy and the shipyard should have had from the very beginning — a Ford-class plan for the development, building, installation and operational training” that’s now needed to avoid such mistakes on the second ship in the four-vessel class, the USS John F. Kennedy, said Mike Fabey, author of “Heavy Metal: The Hard Days and Nights of the Shipyard Workers Who Build America’s Supercarriers.”

© 2022 Bloomberg L.P.

Unlock Exclusive Insights Today!

Join the gCaptain Club for curated content, insider opinions, and vibrant community discussions.

Sign Up
Back to Main
polygon icon polygon icon

Why Join the gCaptain Club?

Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.

Sign Up
close

JOIN OUR CREW

Maritime and offshore news trusted by our 110,236 members delivered daily straight to your inbox.