By Nichola Groom Nov 12 (Reuters) – A federal agency said on Thursday it has again delayed a long-awaited environmental study crucial to permitting the first major U.S. offshore wind project, but final approval of the project is expected by mid-January.
The study of the 800-megawatt Vineyard Wind project planned for the waters off the Massachusetts coast is expected to be released by Dec. 11, according to a government timeline. It had been anticipated later this week.
The document has been repeatedly pushed back since April of 2019 due to concerns that the project’s wind turbines will harm fisheries and navigation.
The delays have been a setback to President Donald Trump’s efforts to fast-track big energy infrastructure projects and have stymied the administration’s plans to launch a promising new domestic industry.
A December publication of the study would pave the way for the administration to issue a final decision on the project by Jan. 15, according to the timeline, just days before Trump leaves office.
A spokesperson for the Bureau of Ocean Energy Management, which is overseeing the permitting process, said the agency was still reviewing the more than 13,000 public comments submitted in response to a supplemental review issued earlier this year.
That study was ordered in 2019 to consider the environmental impacts of many offshore wind farms due to the growing number of projects planned for the East Coast.
“Minor delays like this are not uncommon,” Vineyard Wind spokesman Andrew Doba said in an emailed statement.
Doba said the company was confident that the project would be delivered on time. It is scheduled to be completed in 2023 at the earliest.
Once constructed, the project is expected to generate enough power for more than 400,000 homes. The lease area is located 15 miles off the coast of Martha’s Vineyard.
Vineyard Wind is a joint venture between Copenhagen Infrastructure Partners and Avangrid Inc, the U.S. arm of Iberdrola SA. (Reporting by Nichola Groom; Editing by David Gregorio)
Dive into a sea of information with our meticulously curated weekly “Dispatch” email. It’s more than just a newsletter; it’s your personal maritime briefing.
Dive into a sea of information with our meticulously curated weekly “Dispatch” email. It’s more than just a newsletter; it’s your personal maritime briefing.
Maersk Supply Service has partnered with Edison Chouest Offshore (ECO) to speed up the installation of offshore wind farms in the United States. The partnership centers on unique a windfarm feeder concept...
New York Governor Kathy Hochul has announced the completion of South Fork Wind, America’s first utility-scale offshore wind farm. With all 12 offshore wind turbines constructed, the project is now...
March 13 (Reuters) – Energy firm Equinor on Wednesday announced the first Federal Energy Regulatory Commission (FERC) approval for an offshore wind project to connect directly into the New York City transmission system. FERC on...
March 13, 2024
Total Views: 2270
Why Join gCaptain Club?
Be Informed: Stay updated with the latest maritime news and trends.
Connect: Network with a community of maritime professionals and enthusiasts.
Gain Insights: Receive exclusive content and personal perspectives from our CEO.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.