The Costa Concordia berthed at the port of Genoa, July 27, 2014. Photo courtesy Titan Salvage
By Paola Balsomini
GENOA, Italy, July 27 (Reuters) – The wrecked Costa Concordia cruise liner limped into its last port on Sunday, when it was towed to the northern Italian city of Genoa to be broken up for scrap, two-and-a-half years after running aground and sinking with the loss of 32 lives.
After a four-day journey from the Tuscan island of Giglio, where it sank on Jan. 13, 2012, the 114,500-tonne hulk was manoeuvered into place and secured at the conclusion of one of the largest and most complex maritime salvages ever attempted.
Prime Minister Matteo Renzi flew to Genoa to hail the completion of the operation which restored some pride to Italy after a disaster that was widely interpreted as a national humiliation as well as a human tragedy.
“This isn’t a day for showing off or creating a spectacle, but it’s a mark of gratitude from the prime minister for getting something done which everyone said would be impossible,” Renzi told reporters on the dock, saluting the work of the salvage engineers from Italy and around the world.
“We have had a terrible page to turn, but Italy isn’t a country destined for the scrap heap,” he said.
In contrast to the night when the Concordia ran aground and capsized during a display sometimes performed by cruise ships known as a “salute”, the salvage operation has been a resounding technical success.
After hours of preparation, dockworkers fixed the wreck in place in the industrial port of Voltri, just outside the main harbour in Genoa.
Michael Thamm, CEO of Costa Crociere, congratulates Titan-Micoperi Salvage Master Nick Sloane on a job well done in the control room onboard the Costa Concordia, July 27, 2014. Photo courtesy The Parbuckling Project
It will be dismantled by a consortium led by Italian engineering group Saipem and Genoa-based San Giorgio del Porto in an operation expected to cost 100 million euros and take up to two years.
The overall salvage effort is expected to cost Carnival Corp , owner of the ship’s operator, Costa Cruises and its insurers more than 1.5 billion euros ($2.14 billion).
Floating Hotel
The Costa Concordia, as long as three football pitches laid end to end with 13 passenger decks, was carrying some 4,000 passengers and crew when it went down shortly after the start of a Mediterranean cruise.
Its captain, Francesco Schettino, is on trial for causing the shipwreck, which ended in a chaotic nighttime evacuation during which 32 people died. The body of one crew member lost during the accident has still not been recovered.
Work has proceeded with very few serious hitches since the wreck was brought upright from its position on the rocks last September. That was a multinational effort led by U.S. maritime recovery specialist Titan Salvage which involved as many as 200 crew working on the site at any one time.
After spending the winter months secured in place, the liner was refloated last week and began the voyage of nearly 200 miles to Genoa, which beat rival bids from ports in Italy and Turkey to secure the demolition contract.
Supported by huge “sponsons”, or buoyancy tanks, on either side, the wreck has been towed by two tugboats accompanied by a convoy of auxiliary vessels, travelling at an average speed of around two nautical miles an hour. Helped by calm seas, there were no major alarms during the voyage.
Environment Minister Gian Luca Galletti said concerns in France about possible pollution damage during the transfer, which took the Concordia near Corsica, had proved unfounded. “There hasn’t been any problem at all. They should have a bit more confidence in Italians,” he said. ($1 = 0.7448 Euros) (Writing By James Mackenzie; Editing by Hugh Lawson, Larry King)
Canada will reduce the amount of foreign steel importers can bring into the country tariff-free, a move to help domestic producers suffering from US President Donald Trump’s levies on the sector.
U.S. Transportation Secretary Sean P. Duffy has announced $488 million in awards from the Better Utilizing Investments to Leverage Development (BUILD) grant program, with approximately $35.7 million dedicated to maritime...
Most European ports are lagging in installing the shore-side electrical infrastructure needed for ships to switch from highly polluting marine fuel to cleaner electricity while docked, a new study showed on Tuesday.
July 15, 2025
Total Views: 536
Get The Industry’s Go-To News
Subscribe to gCaptain Daily and stay informed with the latest global maritime and offshore news
— just like 109,000 professionals
Secure Your Spot
on the gCaptain Crew
Stay informed with the latest maritime and offshore news, delivered daily straight to your inbox
— trusted by our 109,000 members
Your Gateway to the Maritime World!
Essential news coupled with the finest maritime content sourced from across the globe.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.