Ruling marks the third federal court this week to block the Trump administration’s offshore wind suspension.
By Blake Brittain and Nichola Groom
NORFOLK, Virginia, Jan 16 (Reuters) – A federal judge on Friday cleared U.S. power company Dominion Energy to resume work on its Virginia offshore wind project, the third legal blow this week to President Donald Trump’s anti-offshore wind agenda.
Judge Jamar Walker of the U.S. District Court for the Eastern District of Virginia issued a temporary order that allows Dominion to restart construction on the $11.2 billion project while its lawsuit against Trump’s Interior Department proceeds.
Earlier this week, offshore wind developers Orsted and Equinor won similar rulings from a U.S. court in Washington in their litigation over Interior’s December 22 suspension of five projects under construction in federal waters.
The government paused the projects due to what it said was new, classified information on risks to national security from radar interference.
At the hearing in Norfolk, Virginia, Walker said Interior’s stop-work order was too broad to address Dominion’s specific project and noted that the risks cited by the government pertained to wind farm operations and not construction.
The Interior Department did not immediately respond to a request for comment on the ruling.
The court decisions in these cases are high stakes for companies and their shareholders because they could allow the multi-billion-dollar projects to be completed, but underlying lawsuits and the administration’s aversion to offshore wind will continue to weigh on the sector.
Offshore wind developers have faced repeated disruptions under Trump, who says wind turbines are ugly, expensive and inefficient.
Dominion has already spent nearly $9 billion on the project and stands to lose $5 million a day during the pause.
The facility has been under construction since 2023 and is expected to provide enough energy to power 600,000 homes.
(Reporting by Blake Brittain in Norfolk, Virginia and Nichola Groom in Los Angeles; Editing by Chris Reese, Rod Nickel)
A string of federal court rulings has effectively unraveled the Trump administration’s attempt to halt offshore wind construction along the U.S. East Coast, with the latest decision clearing Ørsted’s Sunrise...
UK Energy Secretary Ed Miliband signed a landmark clean energy security agreement with European allies on Monday at the North Sea Summit in Hamburg, committing to deliver 100 gigawatts of...
Countries including the UK, Germany and the Netherlands will pledge to jointly develop 100 gigawatts of offshore wind capacity in the North Sea and step up security of such infrastructure amid growing threats of sabotage.
January 23, 2026
Total Views: 746
Get The Industry’s Go-To News
Subscribe to gCaptain Daily and stay informed with the latest global maritime and offshore news
— just like 107,452 professionals
Secure Your Spot
on the gCaptain Crew
Stay informed with the latest maritime and offshore news, delivered daily straight to your inbox
— trusted by our 107,452 members
Your Gateway to the Maritime World!
Essential news coupled with the finest maritime content sourced from across the globe.