Coast Guard Orders Salvage Assessment of ‘Healy’ Engine After Major Failure

Malte Humpert
Total Views: 0
November 24, 2026

The U.S. Coast Guard has sought a specialized salvage inspection of the damaged No. 2 diesel generator aboard USCGC Healy, seeking to identify components that can be reclaimed and reused following a catastrophic engine failure.

The procurement goes well beyond a conventional engine repair contract. The Coast Guard’s October 21 statement of work calls for a comprehensive, component-by-component assessment of the damaged Sulzer 12ZAV40S engine, including measurements against allowable clearances, an evaluation of component wear and identification of parts suitable for reclamation and reuse. The contractor must document its findings in a comprehensive report with high-resolution color photographs.

The Coast Guard announced its intent to award the work on a sole-source basis to Virginia-based Defense Maritime Solutions. The inspection was scheduled for October 26–30 at Coast Guard Base Seattle. The solicitation also included an optional work item, capped at $100,000, to inspect, repair and requalify the engine’s camshaft. The documents do not establish whether that option was exercised or what the inspection ultimately found.

The work follows the July casualty, when Healy suffered a catastrophic overspeed failure of its No. 2 main propulsion diesel generator while operating northwest of Port Angeles, Washington. The vessel was towed to Seattle on July 13. Related procurement documents describe a fire in Generator Room No. 2 that exposed fire-detection equipment and wiring to high temperatures, causing a ground fault and requiring extensive replacement work. The casualty disrupted the cutter’s planned Arctic summer deployment.

The Coast Guard has also been addressing maintenance requirements on engines No. 1 and No. 3. A separate October procurement sought overhaul of their governors and overspeed protection equipment. Both governors had accumulated more than 40,000 operating hours, with no documented service or overhaul history. The work also called for replacing a damaged cylinder head on engine No. 3. The removed head and dummy valve were to be sent to a machine shop for inspection and reconditioning in accordance with original equipment manufacturer specifications.

The Coast Guard specified cylinder head part number 107.122.903.200, National Stock Number 2815-01-465-2075. Separately, supply-chain database records for the part list no active suppliers and indicate that the government does not hold the technical-data rights needed to have alternative manufacturers reproduce it using the proprietary data. The database’s acquisition guidance calls for purchasing directly from the actual manufacturer. This does not establish that the part is unavailable, but it could limit alternative sourcing options if the original manufacturer cannot supply it.

“Most of the machinery systems aboard are antiquated and for some there aren’t even parts,” Vice Commandant of the Coast Guard Admiral Kevin E. Lunday said previously following a fire aboard Healy in 2024.

Engine challenges are not entirely new for Healy. In 2020, a fire damaged the ship’s starboard propulsion motor, forcing it to abandon an Arctic deployment. The Coast Guard replaced the motor with a spare that had been stored at the Coast Guard Yard in Baltimore for 23 years. Moving the roughly 100-ton unit to a California shipyard required a barge voyage through the Panama Canal and removal of part of the ship’s hull for installation.

The latest procurement records do not establish whether the No. 2 diesel generator can be returned to service or which of its components can be recovered. They do, however, show the Coast Guard undertaking a detailed salvage assessment and highlight potential parts-sourcing challenges across the remaining propulsion plant.