Wreck removal crews are continuing work to remove the final two sections of the overturned Golden Ray in St. Simons Sounds.
It’s now been 2 years since the vehicle carrier overturned during a turn as it departed the Port of Brunswick with over 4,100 vehicles inside, an accident the NTSB has now determined was caused by human error that led to inaccurate stability calculations.
The heavy lift vessel VB-10000 continues to hold Section Five of the wreck while the response engineering team modifies the cradle support system on the dry-dock barge. Once the cradle support system is ready, the section will be loaded onto the drydock and moved to a response facility near Mayor’s Point Terminal for further dismantling.
L.ast Friday, the salvage master and the response engineers surveyed the condition of Section Five and prescribed modifications to the cradle support system for the dry-dock barge set to receive the section. The M/V Golden Ray sustained damage when it capsized and listed into a sand bar in 2019.
The cradle support system will ensure the section remains stable for transit to a response facility near Mayor’s Point Terminal, where the section will be partially dismantled.
“The removal plan accounted for possible damage to both Section Five and Section Four,” said wreck removal project manager and naval architect Matt Cooke of T&T Salvage, the lead salvage contractor for the operation. “We are constantly adapting and modifying our approach based on the latest information we receive from the wreck site. The salvage master’s observations are a vital component to the overall engineering process.”
Earlier last week, a weight-shedding team removed 226 vehicles from Section 5, In addition to ensuring a safe lift of the section, weight-shedding also increases the safety of dismantling operations. Any sunken debris that remains inside the Environmental Protection Barrier will be removed after the wreck sections are removed.
Earlier this month, the VB-10000 used large cutting chains to separated Sections Five and Six, marking the the last of seven cuts required for the wreck removal operation. Once each section is separated, the section is then lifted onto a barge for removal, sea-fastening and transport to a recycling facility in Louisiana. All work is being conducted inside an Environmental Protection Barrier constructed around the wreck to catch any pollutants and debris.
While officials initially estimated each cut would take about a day, they quickly realized the complexity of the operation and have been forced to make modifications throughout the process. It’s now been nearly a year since the first cut commenced in November 2020. Additional setbacks have included COVID-19 and hurricane season work stoppages, oil spills and a major fire that threatened the entire operation back in May.
In other Golden Ray news, the NTSB on Tuesday released its highly anticipated report on its investigation into the accident. According to the NTSB, the 656-foot-long Golden Ray began to heel rapidly to port during a 68 degree turn to starboard less than 40 minutes after leaving the Port of Brunswick on September 9, 2019. Despite attempts by the pilot and crew to counter the heel, the rate of turn to starboard increased, and the vessel reached a heel of 60 degrees to port in under a minute before it grounded outside of the channel.
The NTSB determined the probable cause of the capsizing to be the chief officer’s error entering ballast quantities into the stability calculation program, which led to his incorrect determination of the vessel’s stability and resulted in the Golden Ray having an insufficient righting arm to counteract the forces developed during a turn.
All 23 crewmembers and one pilot on board were rescued, including four engineering crew who were trapped in the vessel for nearly 40 hours due to open watertight doors that allowed flooding into the vessel, blocking the primary egress from the engine room where four crewmembers were located. Two crewmembers sustained serious injuries.
The NTSB said damages from the accident were around $200 million, including the total loss of the vessel and $142 million worth of cargo.
Global shipping giant Maersk has released a detailed update on its operations following the collapse of Baltimore’s Key Bridge. The company, which chartered the MV Dali, has now confirmed that...
April 15, 2024: Fourth Body Recovered Another missing victim was recovered at the Key Bridge incident site on April 14, 2024, and was identified today, the Unified Command report. The...
Baltimore City Mayor Brandon M. Scott confirmed that the city is taking legal action against stakeholders of the containership Dali in response to the far-reaching impact of the Key Bridge...
April 15, 2024
Total Views: 2410
Why Join the gCaptain Club?
Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.