Allseas’ giant installation/decommissioning and pipelay vessel Pioneering Spirit successfully executed her maiden heavy lift project on Monday with the removal of the 13,500 ton Yme mobile offshore production unit (MOPU) in the North Sea.
Allseas said in a statement Monday that the job demonstrates the unique single-lift capability of the Pioneering Spirit. The dynamically positioned, catamaran-like Pioneering Spirit was designed in-house by Swiss-based Allseas for single-lift installation and removal of large offshore oil and gas platforms, and the installation of oil and gas pipelines.
Photo: Allseas
At 382 meters long and 124 meters wide, the Pioneering Spirit is one of the largest ships ever constructed. At the bow it features a 122 m long by 59 m wide slot that enables the vessel to straddle a platform and remove entire topsides in a single lift using eight sets of horizontal lifting beams. The vessel features a topside lift capacity of 48,000 tons, making it one of the most capable heavy-lift ships in the world.
Photo: AllseasPhoto: Allseas
The Pioneering Spirit was built in South Korea by Daewoo Shipbuilding and Marine Engineering and arrived in Rotterdam for final outfitting in January 2015. The vessel has been under construction since at least 2010, but its concept design for actually dates back nearly 30 years, and was based on two tankers placed side-by-side. Edward Hereema has called the vessel one of the biggest bets of his career – rumored to cost some $3 billion to build.
The vessel was originally named Pieter Schelte after offshore heavy lifting pioneer Pieter Schelte Heerema (1908–81), the father of Allseas’ founder Edward Hereema, but the vessel was renamed in February 2015 amid public outcry over the vessel’s namesake being a convicted Nazi war criminal.
Photo: AllseasPhoto: AllseasPhoto: Allseas
The Yme platform is located about 62 miles off the coast of Norway in the central part of the North Sea. The platform, which has never actually produced any oil, was previously operated by Canada’s Talisman but is now owned by Repsol. It has been unmanned since 2012 after cracks were found in the platform’s legs.
The Yme platform is a jack-up type platform standing on three steel legs of 3.5 meter diameter, which are inserted approximately 10 meters inside the subsea storage tank columns at 93 meters water depth. The platform is now fastened on board and the Pioneering Spirit, headed to the newly developed dismantling yard in Lutelandet, Norway.
Photo: AllseasPhoto: Allseas
Pioneering Spirit Specifications
Length overall (incl. stinger): 477 m (1,565 ft)
Length overall (excl. stinger): 382 m (1,253 ft)
Length between perpendiculars: 370 m (1,214 ft)
Breadth: 124 m (407 ft)
Depth to main deck: 30 m (98 ft)
Slot length: 122 m (400 ft)
Sloth width: 59 m (194 ft)
Topsides lift capacity: 48,000 t
Jacket lift capacity: 25,000 t
Operating draught: 27 m
Maximum speed: 14 knots
Total installed power: 95,000 kW
Thrusters: 12 x 6050 kW non-retractable, fixed pitch, variable speed azimuth type
Dynamic positioning system: LR DP (AAA), fully redundant Kongsberg K-Pos DP-22 and 2 x cJoy system
Accommodation: 571 persons
Helideck: Maximum take-off weight 12.8 t, suitable for Sikorsky S-61 and S-92 helicopters
Deck cranes: Special purpose crane of 5000 t (11,000 kips)
Special purpose crane of 600 t (1300 kips)
3 x pipe transfer cranes of 50 t (110 kips)
Work stations: Double-joint factory (with 5 line-up stations and 2
stations for combined external and internal welding)
Firing line with 6 welding stations for double joints, 1
NDT station and 6 coating stations
Installed tension capacity: 4 x 500 t (4 x 1100 kips)
Pipe cargo capacity on main deck: 27,000 t
Pipe diameters: From 2″ to 68″ OD
Classifications: 100 A1 Heavy lift and heavy cargo ship, upper deck aft of frame 43 strengthened for load of 15 t/m²; helicopter landing area, LA, *IWS, LI, EP (B, G, N, O, P, S), ice class 1C FS LMC, DP (AAA), PSMR* with following descriptive note: Pipelaying vessel Shipright (BWMP), split bow forward of frame 99
Equinor expects 10-20% production decline at Johan Sverdrup, Europe's largest oil field growth source. The decline signals broader challenges for global oil supply amid aging fields.
UK Energy Secretary Ed Miliband signed a landmark clean energy security agreement with European allies on Monday at the North Sea Summit in Hamburg, committing to deliver 100 gigawatts of...
Countries including the UK, Germany and the Netherlands will pledge to jointly develop 100 gigawatts of offshore wind capacity in the North Sea and step up security of such infrastructure amid growing threats of sabotage.
January 23, 2026
Total Views: 757
Get The Industry’s Go-To News
Subscribe to gCaptain Daily and stay informed with the latest global maritime and offshore news
— just like 107,340 professionals
Secure Your Spot
on the gCaptain Crew
Stay informed with the latest maritime and offshore news, delivered daily straight to your inbox
— trusted by our 107,340 members
Your Gateway to the Maritime World!
Essential news coupled with the finest maritime content sourced from across the globe.