Crews Start Cutting Second Section of Golden Ray

The vessel WINNIE holds its position outside the Environmental Protection Barrier (EPB) during routine on-water pollution mitigation operations. Photo: St. Simons Sound Incident Response

Crews Start Cutting Second Section of Golden Ray

Mike Schuler
Total Views: 18295
December 28, 2020

Crews working to cut up and remove the Golden Ray in St. Simons Sound, Georgia have started cutting the stern section, known as “Section Eight”.

The cutting comes after crews successfully cut off and removed the bow section in November, marking the first section to be removed. Crews have since been working on modifications to make the operation more efficient based on lessons learned from the first section.

“We are confident that the time invested to implement modifications to the cutting apparatus as well as perform critical maintenance to the wreck removal equipment will contribute to a safe and efficient cutting operation.” said Incident Commander Chris Graff of Gallagher Marine Systems, “We are ready to mitigate expected debris and other potential threats. The operation may be loud at times and please respect the safety zones around the wreck site.”

The next cutting comes after divers completed the drilling of additional drainage holes along the stern of the Golden Ray in order to maintain stability and even distribution of weight when lifted.

Meanwhile, Section One of the Golden Ray has began its transit to a recycling facility in Louisiana onboard the Barge JULIE B. Once the recycling facility receives Section One, the barge will return to Brunswick, Ga. and standby to receive the next section.

A 150-yard safety zone around the Environmental Protection Barrier has increased to 200 yards for recreational vessels. The Unified Command advises mariners to please steer clear of the perimeter and also continues to phohibit any unauthorized usage of drones around the wreck site.

The Unified Command has a flotilla of up to 36 vessels outside the EPB to monitor and protect against any pollution that escapes into the environment.

The Golden Ray was carrying about 4,200 vehicles when it lost stability and grounded in St. Simons Sound in Georgia as it departed the Port of Brunswick in September 2019. All vehicles remain inside the ship’s cargo holds and are being cut along with the wreck’s hull.

Related: Section One of Golden Ray Wreck Cut and Lifted Onto Barge

Unlock Exclusive Insights Today!

Join the gCaptain Club for curated content, insider opinions, and vibrant community discussions.

Sign Up
Back to Main
polygon icon polygon icon

Why Join the gCaptain Club?

Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.

Sign Up
close

JOIN OUR CREW

Maritime and offshore news trusted by our 105,943 members delivered daily straight to your inbox.

gCaptain’s full coverage of the maritime shipping industry, including containerships, tankers, dry bulk, LNG, breakbulk and more.