Join our crew and become one of the 109,246 members that receive our newsletter.

Virginia class submarine comissioning at electric boat shipyard in Rhode Island

The crew of the pre-commissioning unit (PCU) Idaho (SSN 799) march in formation during a christening ceremony at General Dynamics Electric Boat shipyard facility in Groton, Conn., March 16, 2024. (U.S. Navy photo by John Narewski)

Virginia Class Submarine Program $17B Over Budget—Enough to Build a New Aircraft Carrier

Bloomberg
Total Views: 0
September 20, 2024


The Virginia-class submarine project may exceed its budget by $17 billion—surpassing the price tag of an entire new aircraft carrier.

By Tony Capaccio (Bloomberg) The Navy’s new Virginia-class submarines are projected to run $17 billion over their planned budget through 2030, a problem emblematic of a crisis in the program, the House’s top lawmaker on defense spending disclosed.

“It’s clear that the Navy and shipbuilders have known about this shortfall for at least 18 months” but “Congress was notified just two weeks ago,” Representative Ken Calvert, chairman of the House defense appropriations subcommittee, said in remarks released Thursday before a classified hearing with Navy Secretary Carlos Del Toro.

The program for a new generation of nuclear-powered subs being manufactured by General Dynamics Corp. and HII “has slipped two to three years” behind schedule “and is experiencing extraordinary cost growth,” Calvert said. The $17 billion shortfall will increase the program’s projected $184 billion total cost if the Navy can’t close the gap by finding ways to cut expenditures.

Also read: Here’s Why the US Navy Needs More Virginia-Class Submarines Now

Several Navy ship programs, including the Virginia class, “are in crisis,” he said. Calvert, a California Republican and usually an enthusiastic supporter of defense programs, lambasted the Navy for what he called a lack of candor in disclosing problems and for poor metrics in overseeing multibillion-dollar programs.

“It’s not clear to me that anyone has accurate information about the trajectory of any shipbuilding program other than the program executive officers — and since they switch out every two years, the options for long-term accountability are limited,” Calvert said. “For too long, this committee has been put in a position of asking what the Navy is hiding behind the curtain. It’s time to pull down the curtain altogether,” he said.

The Navy said in a statement after the hearing that Del Toro “has been advocating for improvements to the maritime industrial base, and to increase funding to ensure the Navy meets its acquisition objectives.” 

To demonstrate fiscal responsibility, the Navy has set up “an independent Naval Cost Agency to improve cost estimations and created a Maritime Industrial Base program to manage the funding supporting the industrial base,” according to the statement. The Navy said it’s working to improve ship design processes and investing in modern facilities.

Also read: U.S. Navy Commissions First Submarine Designed for Coed Crews

General Dynamics did not immediately respond to requests for comment made after normal business hours on Thursday. A representative for HII said the company would comment before House members on Friday.

The Virginia-class submarine is armed with both torpedoes and land-attack missiles and, starting later this year, with anti-ship Tomahawk cruise missiles. The vessels are intended to give the US a crucial advantage in any conflict with China.

Aukus Risk

Overall, delivery dates for Virginia-class subs are running an estimated 24 to 36 months past the contracted dates, according to the Navy’s 45-day ship review released in April. General Dynamics and HII are supposed to be completing two submarines a year but instead are averaging the completion of one plus 20% of the work building a second sub. The Navy projects the contractors won’t hit the two-a-year rate by 2028.

The Virginia-class delays could undermine the Aukus partnership involving the US, Australia and the UK if they aren’t reversed soon.

Under the Aukus agreement, starting in about 2032 the US Navy is supposed to sell Australia the first of as many as five existing or new Virginia-class subs. Those vessels would fill a gap until delivery in the late 2030s of the first new vessels to be built in the UK and Australia with technology from the US and UK.

(Updates with companies being asked for comment, in eighth paragraph.)

© 2024 Bloomberg L.P.

Unlock Exclusive Insights Today!

Join the gCaptain Club for curated content, insider opinions, and vibrant community discussions.

Sign Up
Back to Main
polygon icon polygon icon

Why Join the gCaptain Club?

Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.

Sign Up
close

JOIN OUR CREW

Maritime and offshore news trusted by our 109,246 members delivered daily straight to your inbox.

Join Our Crew

Join the 109,246 members that receive our newsletter.