By Tony Capaccio (Bloomberg) The Navy’s new Virginia-class submarines are projected to run $17 billion over their planned budget through 2030, a problem emblematic of a crisis in the program, the House’s top lawmaker on defense spending disclosed.
“It’s clear that the Navy and shipbuilders have known about this shortfall for at least 18 months” but “Congress was notified just two weeks ago,” Representative Ken Calvert, chairman of the House defense appropriations subcommittee, said in remarks released Thursday before a classified hearing with Navy Secretary Carlos Del Toro.
The program for a new generation of nuclear-powered subs being manufactured by General Dynamics Corp. and HII “has slipped two to three years” behind schedule “and is experiencing extraordinary cost growth,” Calvert said. The $17 billion shortfall will increase the program’s projected $184 billion total cost if the Navy can’t close the gap by finding ways to cut expenditures.
Several Navy ship programs, including the Virginia class, “are in crisis,” he said. Calvert, a California Republican and usually an enthusiastic supporter of defense programs, lambasted the Navy for what he called a lack of candor in disclosing problems and for poor metrics in overseeing multibillion-dollar programs.
“It’s not clear to me that anyone has accurate information about the trajectory of any shipbuilding program other than the program executive officers — and since they switch out every two years, the options for long-term accountability are limited,” Calvert said. “For too long, this committee has been put in a position of asking what the Navy is hiding behind the curtain. It’s time to pull down the curtain altogether,” he said.
The Navy said in a statement after the hearing that Del Toro “has been advocating for improvements to the maritime industrial base, and to increase funding to ensure the Navy meets its acquisition objectives.”
To demonstrate fiscal responsibility, the Navy has set up “an independent Naval Cost Agency to improve cost estimations and created a Maritime Industrial Base program to manage the funding supporting the industrial base,” according to the statement. The Navy said it’s working to improve ship design processes and investing in modern facilities.
General Dynamics did not immediately respond to requests for comment made after normal business hours on Thursday. A representative for HII said the company would comment before House members on Friday.
The Virginia-class submarine is armed with both torpedoes and land-attack missiles and, starting later this year, with anti-ship Tomahawk cruise missiles. The vessels are intended to give the US a crucial advantage in any conflict with China.
Aukus Risk
Overall, delivery dates for Virginia-class subs are running an estimated 24 to 36 months past the contracted dates, according to the Navy’s 45-day ship review released in April. General Dynamics and HII are supposed to be completing two submarines a year but instead are averaging the completion of one plus 20% of the work building a second sub. The Navy projects the contractors won’t hit the two-a-year rate by 2028.
The Virginia-class delays could undermine the Aukus partnership involving the US, Australia and the UK if they aren’t reversed soon.
Under the Aukus agreement, starting in about 2032 the US Navy is supposed to sell Australia the first of as many as five existing or new Virginia-class subs. Those vessels would fill a gap until delivery in the late 2030s of the first new vessels to be built in the UK and Australia with technology from the US and UK.
By Tony Capaccio May 30, 2025 (Bloomberg) –The US Navy will start fielding an anti-ship version of its Tomahawk cruise missile on destroyers by late September in what the service’s readiness...
St. Johns Ship Building, a Florida-based shipyard owned by Americraft Marine, has been awarded its first U.S. Navy shipbuilding contract to construct a Dive Support Vessel (DSV). The contract marks...
South Korean conglomerate Hanwha Group is reportedly planning a major investment for improvements at its recently acquired Philly Shipyard, with plans to produce the U.S.-built LNG carriers. According to Korean...
May 20, 2025
Total Views: 2220
Get The Industry’s Go-To News
Subscribe to gCaptain Daily and stay informed with the latest global maritime and offshore news
— just like 108,990 professionals
Secure Your Spot
on the gCaptain Crew
Stay informed with the latest maritime and offshore news, delivered daily straight to your inbox
— trusted by our 108,990 members
Your Gateway to the Maritime World!
Essential news coupled with the finest maritime content sourced from across the globe.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.