The Costa Concordia moored at the “Seawall” pier in the Port of Prà Voltri, Genoa, Italy. Photo: Ship Recycling Consortium
More than three years after the Costa Concordia ran aground in Giglio, the effort to dismantle and recycle the Costa Concordia continues nearly around-the-clock in Italy.
The Costa Concordia arrived in Genoa in July 2014 following the historic salvage project. Since then, the Costa Concordia has been moored in the Port of Prà Voltri, Genoa, where the initial phases of dismantling/scrapping project will take place. Even now, the Costa Concordia remains afloat by means of the 30 sponsons that played a key role in the parbuckling, refloating and towing phases of the salvage.
The dismantling project is being carried out by the “Ship Recycling Consortium”, which is made up of the Italian company Saipem (51%) and San Giorgia del Porto (49%). The project is expected to last for a total of about 22 months and will involve between 100 and 250 personnel working at any given time. As was the case with salvage, safeguarding the environment and all personnel involved will be of paramount importance throughout the entire project.
With the wreck now in Genoa, the Ship Recycling Consortium has already drafted and presented a “Ship Recycling Plan” detailing the four phases of the dismantling project, which includes a detailed Waste Management Plan illustrating the procedures for the disposal/recycling/reuse of all the materials obtained.
According to the Consortium, the dismantling work is being carried out with the aim of recycling approximately 80% of the discarded materials, including about 50,000 tonnes of steel and other metals which are to be obtained from the wreck.
Detailed below are the 4 Phases of the Costa Concordia Dismantling Project:
Phase 1: Arrival and Stripping
Phase 1 began with the mooring of the Costa Concordia at the “Seawall” pier in the Port of Prà Voltri on July 27, 2014. After being handed over by the salvage consortium Titan Micoperi, the Ship Recycling team got to work performing important operations related to yard safety and preparations for the initial ship breaking and stripping of the interiors. Specifically, these initial tasks included:
Installation of the shipboard fire-fighting system
Completion of the lighting system
Installation of the necessary wiring and electrical installations
Installation of elevators for transportation of materials
Safety measures – e.g. repair of the gunwale/bulwarks, closure of certain shafts and spaces, protective measures in stairways, installation of gangways affording access to the ship
Installation of one crane on the lido deck (about 60 meters in height) and another one forward for lifting materials
Creation of openings required to remove materials and load them on barges for transportation to a dedicated area of the port
Winterization of mooring arrangements (in case of adverse weather conditions during the winter season).
Behind the scenes, all the administrative procedures have been carried out in order to obtain the permits and authorizations required, the last of which was duly issued on October 9, 2014, the Consortium said.
The Porto di Prà Voltri location consists of two separate worksites: the “Seawall”, chosen for initial mooring of the wreck, and the pier at the far end of the “Banchina di Voltri” quay, where facilities have been set up for logistics operations and waste management.
The initial ship breaking involves the stripping and removal of the furnishings and fittings of the decks above water, beginning with the highest decks and working down. One of the primary goal’s of this first phase is to reduce the draft of the wreck, which will allow for the ship to be moved to the “Molo Ex Superbacino” dock where phases two and three of the project will take place.
The Consortium estimates that about 8,000 to 10,000 tonnes of material will need to be removed prior to the transfer. Phase 1 is expected to be completed in the first few months of 2015 (possibly March) and involves up to 200 people.
Phase 2: Transfer to the “Molo Ex Superbacino” Dock and Dismantling of Decks
Once the Costa Concordia reaches the required draft, the wreck will be moved from the “Seawall” pier to the “Molo Ex Superbacino” dock. Here, personnel will work to dismantle the structures of decks 14 to 2, including the stripping of interior furnishings and fittings on the decks.
The Consortium notes that during this phase, the deck structures will be removed in such a way as not to adversely impact the stability or longitudinal strength of the hull.
Phase 3: Preparation for Transfer to Dry Dock
The main objective of Phase 3 will be to create buoyancy by making several compartments of the ship watertight and possibly installing airbags. By doing so, the Consortium will be able to remove the 30 sponsons before towing the wreck to dry dock, where final dismantling will take place.
Phase 3 will also involve cleaning the food storerooms and cold storage room on deck 0.
Phase 4: Final Dismantling Operations
Final dismantling operations are to take place in a segregated area of what is known as Dry Dock no. 4, where the wreck will be towed at the end of Phase 3. Once there, Phase 4 will involve the complete disassembly of the wreck, including the removal of all interior fittings, the clean-up of additional areas, and final demolition of the remaining structures.
Phase 4 will conclude with the appropriate handling, disposal and recycling of the discarded materials.
Below is a video showing some illustrations of the phases:
More information on the Costa Concordia Dismantling Project can be found at the Consortium’s website: http://shiprecycling.it/.
Panama's President Jose Raul Mulino responded "be serious, be serious" on Wednesday when asked in Davos whether he was concerned the U.S. would invade after President Donald Trump said he would take back the Panama Canal.
WASHINGTON, Jan 21 (Reuters) – The Trump administration has fired U.S. Coast Guard Commandant Admiral Linda Lee Fagan, the first female uniformed leader of an Armed Forces branch, for putting diversity issues over border security,...
HELSINKI, Jan 16 (Reuters) – The Eagle S tanker seized by Finnish authorities on suspicion of ripping up subsea cables will not face a separate criminal investigation into whether its fuel cargo violates sanctions...
January 16, 2025
Total Views: 1305
Sign Up Now for gCaptain Daily
We’ve got your daily industry news related to the global maritime and offshore industries.
JOIN OUR CREW
Maritime and offshore news trusted by our 108,948 members delivered daily straight to your inbox.
Your Gateway to the Maritime World!
Essential news coupled with the finest maritime content sourced from across the globe.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.