MADRID, Jan 11 (Reuters) – Sacyr, the Spanish building company leading a consortium to expand the Panama Canal, said it risks losing $574 million in guarantees and advance payments if a spat over cost overruns at the multi-billion dollar project is not resolved.
In an 8-page document sent on Friday to Spain’s stock market regulator but which had not been made public until Saturday, the firm also detailed for the first time its claims of $1.6 billion in extra costs and said the canal extension would not be completed until June 30, 2015 at the earliest.
The consortium warned earlier this month it would halt work from Jan. 20 on a third set of locks for the century-old waterway, one of the world’s largest building contracts, unless the Panama Canal Authority footed the bill.
In an interview with Reuters, Sacyr Chairman Manuel Manrique on Friday played down the row and said the company was making progress in talks with the canal operator over financing to avoid a damaging work stoppage.
Sacyr said the guarantees it provided on the contract were worth $445.5 million as of Dec. 31, 2013 and it had also made advance payments worth $128.4 million.
The company said it registered in 2012 a 665-million-dollar income based on cost overruns it had not yet been paid but hoped to cash in. It added it did not register any additional income linked to its claims as of Sept. 30, 2013.
The consortium, which made a 289-million-dollar loss in 2012, has been paid 2.05 billion dollars for the work completed so far, or 66 percent of the $3.2 billion contract, as well as 784 million dollars in advance payments.
Sacyr insisted in the document it had over the last five months repeatedly asked the canal authority to start a constructive dialogue over the overruns which, it said, arose only after the work started.
“The overruns that are being claimed correspond to situations that appeared after the work started, which is when the inaccuracy of the information provided to the consortium to execute the project was verified,” the Spanish firm said.
It added that the canal operator and international experts audited the overruns in March 2013 and said they were “real, reasonable and in line with the market.”
Among the main claims brought by Sacyr is an $880 million extra cost due to “fundamental and irreversible changes” to the original project made by the Panama Canal Authority.
Another $497 million overrun arose because the basalt found locally, in contradiction with the documentation provided at the time of the tender, was not right for the mix of concrete planned for the locks, meaning the consortium had to bring in basalt from elsewhere.
A further $120 million, which was added to the cost of building a temporary dam, was originated by inaccurate geologic information in the contract, Sacyr also said.
by John Konrad (gCaptain) In a move to tackle an acute mariner shortage accentuated by the rapid retirement of boomers, Canada has signed an unprecedented agreement with the Philippines, allowing...
SYDNEY, April 22 (Reuters) – Australia’s Defence Minister Richard Marles said on Saturday that the wreck of a Japanese merchant ship, sunk in World War Two with 864 Australian soldiers on board,...
For more than 30 years, researchers have been exploring the depths of Lake Superior in search of vessels lost to time. The area off the coast of Grand Marais, Michigan,...
April 17, 2023
Total Views: 13792
Sign Up Now for gCaptain Daily
Just enter your email and get hot news every morning
Let gCaptain be your compass for maritime news
The news that you need delivered every morning.
Sign Up Now for gCaptain Daily
We’ve got your daily industry news related to the global maritime and offshore industries.
OUT AT SEA?
We’ve got you covered with trusted maritime and offshore news from wherever you are.
OUT AT SEA?
We’ve got you covered with trusted maritime and offshore news from wherever you are.
We use cookies on our website to give you the most relevant experience. By clicking “Accept”, you consent to the use of ALL the cookies.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
{"Tags":["panama canal","panama canal expansion"],"Categories":["Maritime News"],"Excerpt":"Sacyr, the Spanish building company leading a consortium to expand the Panama Canal, said it risks losing $574 million in guarantees and advance payments if a spat over cost overruns at the multi-billion dollar project is not resolved."}