Join our crew and become one of the 104,332 members that receive our newsletter.

Photos: First Johan Sverdrup Topside Installed in North Sea

Photos: First Johan Sverdrup Topside Installed in North Sea

GCaptain
Total Views: 37
April 26, 2018

The final madule of the Johan Sverdrup riser platform lifted in place by the heavy-lift vessel “Thialf”. Photo taken April 21, 2018. Photo: Woldcam – Roar Lindefjeld / Bo Randulff / Statoil

The final module of the Johan Sverdrup riser platform was lifted into place by the heavy lift vessel Thialf. With the installation, the first of four topsides making up the next North Sea giant is starting to really take shape.

“It’s a special feeling to see the first Johan Sverdrup platform in place, even a few days ahead of the plan set more than three years ago – all without any serious incidents along the way. This is a testament to the high quality in execution of the project so far, which again is a result of the good collaboration between thousands of people at our suppliers, partners and Statoil”, says senior vice president for Johan Sverdrup, Kjetel Digre.

The riser platform – the first of four platforms to be installed in the first phase of the project – handles all exports of oil and gas from the Johan Sverdrup field. The power converter, which will enable the Johan Sverdrup field to be powered with renewable electricity from shore, will also be located on the platform.

This makes the riser platform a particularly central piece of the Johan Sverdrup field center. Not only will about 660,00 barrels of oil and gas pass per day through the platform during peak production, but power from shore will also make Johan Sverdrup one of the most carbon efficient fields on the Norwegian continental shelf.

Built in record speed

The riser platform topside was built by Samsung Heavy Industries in three modules, based on the design and engineering of Aker Solutions. Steel cut took place at the yard in South Korea on 30 June 2016. Nineteen months later, in February 2018, the Dockwise White Marlin with two main modules onboard set sail towards Norway. Three weeks later, the third and final main module followed suit on the Dockwise Mighty Servant 3.

Once the vessels had safely arrived at the destination in the North Sea, all the pieces of the platform puzzle were lifted in place by the heavy-lift vessel Thialf of Heerema Marine Contractors.

Here are some photos from the installation: 

April 20, 2018. Photo: Roar Lindefjeld / Bo Randulff / Statoil
Woldcam – Roar Lindefjeld / Bo Randulff / Statoil
Woldcam – Roar Lindefjeld / Bo Randulff / Statoil
Woldcam – Roar Lindefjeld / Bo Randulff / Statoil
Woldcam – Roar Lindefjeld / Bo Randulff / Statoil
Woldcam – Roar Lindefjeld / Bo Randulff / Statoil
Photo: Woldcam – Roar Lindefjeld / Bo Randulff / Statoil

Ståle Nordal, Statoil’s project manager for the riser platform, is very pleased to see the platform fully assembled at the Johan Sverdrup field. The construction has been a success in terms of time, cost and quality, but also in terms of safety. All in all, the construction has taken about 7 million hours, and with zero serious incidents.

The key to success, according to Nordal, is thorough preparations and learning from other projects built in South Korea, as well as a supplier fully committed from day one in Samsung Heavy Industries.

“Delivering a topside of this size and complexity in less than 20 months, and without a single serious incident, is a feat on its own,” says Nordal.

Busy installation campaign

Johan Sverdrup rendering. Photo: Statoil

The installation of the riser platform marks the beginning of one of the most hectic installation programs ever for a project in Statoil. More than 400 km of pipelines, 200 km of power cables, the drilling platform, two jackets and a bridge, will be installed during the next weeks and months.

And in early May the offshore organization, which will grow to as many as 2,400 people spread across three shifts at its peak, will initiate the important work of connecting and hooking up the growing field center and starting to prepare for production start-up late in 2019.

“With this milestone we firmly take a step into the final phase of the project. These operations have been carefully planned, drawing on Statoil’s significant experience in this area. Even so, given the significant installation scope in the Johan Sverdrup project we’re entering into an exciting but complex period, with safety always as the highest priority. With the riser platform in place, however, we have taken a significant step forward in preparation for start-up late next year,” says Digre.

Unlock Exclusive Insights Today!

Join the gCaptain Club for curated content, insider opinions, and vibrant community discussions.

Sign Up
Back to Main
polygon icon polygon icon

Why Join the gCaptain Club?

Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.

Sign Up
close

JOIN OUR CREW

Maritime and offshore news trusted by our 104,332 members delivered daily straight to your inbox.

Join Our Crew

Join the 104,332 members that receive our newsletter.