Gibdock Completes Major LNG Conversion on Baleària Ferry Napoles

gCaptain
Total Views: 63
May 10, 2019

The converted Nápoles alongside at Gibdock before reentering service with Baleària

Gibraltar’s Gibdock shipyard has completed a major conversion project on the Baleària ferry Napoles, converting the vessel LNG fuel.

The three-month conversion project was one of the largest projects ever undertaken by the shipyard, located on the Mediterranean side of the Strait of Gibraltar.

The 186m long Napoles, which has capacity for 1,600 passengers and 1,430 lane meters of cargo, is the first of five ships that Baleària plans to convert to dual fuel operations to comply with IMO’s 2020 sulphur cap regulations.

Gibdock has already secured a contract to convert a second vessel, Sicilia, which is due to arrive at the yard later this year.

”Baleària is a longstanding client for scheduled repair and maintenance work, so it made perfect sense to carry out the conversion at Gibdock,” said Richard Beards, Managing Director of Gibdock. “We are delighted to have been entrusted with this landmark project, which was a first for us and for Baleària; the experience will ensure that the Sicilia conversion goes even more smoothly.”

gibdock shipyard aerial

Napoles arrived at Gibdock in November. By that time, the yard already having pre-fabricated two LNG bunker fuel reception stations for later installation. The majority of the remaning work took place alongside the yard’s main repair wharf. Some elements of the conversion also took place in Gibdock’s Panamax size Dock No.1.

Gibdock says the project required extensive modifications to the ferry’s Deck 1 to accommodate the 200 tonne, 27m x 6m diameter LNG fuel tank from Wärtsilä. Gibdock also cropped Decks 5 through to 2 to create a route through which to lower the 400m3 capacity tank.

Another key part of the project was the modification of the MAN 9L 48/60-A main engines, which was undertaken by engineers from MAN Primeserv. Now designated 9L 51/60DFF, Gibdock assisted modifications made by the manufacturer with auxiliary pipework and steel structures in connection with reassembly, also fitting specialised valves, a compressor and generator unit.  Extensive automation system and cabling work was also carried out by Gibdock technicians.

After its departure, Napoles began working on a new passenger and Spanish freight route connecting Huelva and the Canary Islands.

“We already have substantial experience with ballast water treatment and scrubber retrofits, and now we have an LNG dual conversion under our belt,” says Beards. “Our range of solutions for forthcoming IMO regulatory changes is comprehensive in suiting any vessel type, age and route profile.

Unlock Exclusive Insights Today!

Join the gCaptain Club for curated content, insider opinions, and vibrant community discussions.

Sign Up
Back to Main
polygon icon polygon icon

Why Join the gCaptain Club?

Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.

Sign Up
close

JOIN OUR CREW

Maritime and offshore news trusted by our 110,467 members delivered daily straight to your inbox.