FILE PHOTO: A support vessel is seen next to a wind turbine at the Walney Extension offshore wind farm operated by Orsted off the coast of Blackpool, Britain September 5, 2018. REUTERS/Phil Noble
By Nichola Groom July 29 (Reuters) – Trump administration infighting is holding up approval of the first major U.S. offshore wind energy project, with agencies sparring over whether the proposal does enough to protect the fishing industry, according to interviews and agency documents.
The delays are a setback to President Donald Trump’s efforts to fast-track big energy infrastructure projects and could threaten the administration’s plans to launch a promising new domestic industry.
How the problem is resolved will shape the regulatory blueprint for a growing list of offshore wind developers seeking to tap in to rising U.S. demand for renewable energy, but who face objections from fishermen worried the turbines will affect commercial species or make fishing more difficult.
The Trump administration has sought to fire up development of the nascent offshore wind industry by streamlining permitting and carving out areas off the coast for leasing – part of its policy to boost domestic energy production and jobs.
Vineyard Wind, a joint venture between Copenhagen Infrastructure Partners and Avangrid Inc, was scheduled to begin construction this year 14 miles (23 km) off the coast of Massachusetts to power more than 400,000 homes by 2021 – making it the first large-scale offshore wind development in the United States.
But a federal environmental study crucial to its permitting has been repeatedly delayed since April, according to published government timelines, without any public explanation from Trump administration officials. Vineyard Wind has said the delays could threaten the project’s viability.
Documents seen by Reuters, which have not previously been made public, show the National Oceanic and Atmospheric Administration’s (NOAA) National Marine Fisheries Service (NMFS) triggered the delays by declining to sign off on the project’s design, as proposed by the Bureau of Ocean Energy Management (BOEM), the lead agency on offshore wind projects.
Under a 2017 Trump executive order aimed at limiting environmental reviews for major infrastructure projects to two years, federal agencies must request support from cooperating agencies at three points in the review process, including before issuing the final environmental impact study.
Getting the support allows the process to move more quickly, but failing to get it can force further analysis.
SEEKING AGREEMENT ON FISHING
In an April 16 letter to BOEM, Michael Pentony, regional administrator for NOAA Fisheries’ Greater Atlantic office, said his agency could not support the environmental permit for Vineyard Wind because the project failed to fully address the concerns of the fishing industry.
For example, he said, the fishing industry had asked for wider spacing between turbines than the 0.75 nautical mile laid out in the proposal, and wanted the turbines aligned in an east-west orientation, rather than northwest-southeast.
He also said the proposal relied on undefined measures to compensate fishermen for potential damage to their livelihoods caused by the wind farm. The issues “require detailed analysis” not currently conducted in the study.
In a written response to Pentony, seen by Reuters, BOEM Chief Environmental Officer William Brown said the fishing industry’s concerns “do not rise to the level that would justify the likely extensive project delays and potential failure of the project.”
He added that BOEM could try to issue the environmental permit without the support of the National Marine Fisheries Service: “We hope that, on reflection, NMFS will concur with our conclusion. If NMFS does not concur, however, we are prepared to note its non-concurrence in the final EIS (environmental impact statement) and the (Record of Decision),” Brown wrote.
Three months later, the agencies have yet to resolve their differences.
“At this time, we are not yet able to come to a point of concurrence,” NOAA spokesman John Ewald said in an emailed statement last week. Because Vineyard Wind is the first such project to undergo the federal environmental review process, Ewald said NOAA “wants to ensure that impacts to ocean resources are fully addressed.”
BOEM spokesman Stephen Boutwell said NMFS is required to co-sign the project’s Record of Decision, a formal decision document, for the permit to be issued. The final environmental impact study and record of decision had originally been expected in April but were later delayed to June and then early July. Boutwell said the agency does not “have a date for these publications at this time.”
Vineyard Wind said earlier this month that it told federal officials it would be “very challenging” to move forward with the project in its current configuration if the environmental permit is not issued within four to six weeks. The company wants to start construction soon to lock in a federal tax credit that expires next year. The credit is currently worth 12% of the value of the project.
NOAA is a division of the U.S. Department of Commerce, while BOEM falls under the Department of Interior. (Reporting by Nichola Groom in Los Angeles Editing by Richard Valdmanis and Matthew Lewis)
by Captain John Konrad (gCaptain) On a crisp morning that should have promised smooth sailing, Captain Mike Vinik found himself staring at a maze of steel and concrete where open water used...
by Sachin Ravikumar (Reuters) Immigration tops the list of issues that Britons consider most important for the first time since 2016 – when Britain voted to leave the European Union...
New York Maritime College’s new training ship, Empire State VII, is canceling its planned European port visits during its maiden summer cruise and returning to the western Atlantic. The decision...
July 6, 2024
Total Views: 7721
Why Join the gCaptain Club?
Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.