Join our crew and become one of the 110,264 members that receive our newsletter.

mariner oil field equinor

Equinor Again Delays Start-Up of Britain’s Mariner Offshore Oilfield

Reuters
Total Views: 76
April 10, 2019

The Mariner field is located in the North Sea approximately 95 miles east of Shetland. It has recoverable reserves estimated at 300 million barrels of oil. Photo: Equinor

reuters logo By Nerijus Adomaitis OSLO, April 10 (Reuters) – The operator of the Mariner heavy oil field, one of Britain’s largest offshore developments in years, postponed its start-up to summer 2019 on Wednesday for safety checks on the platform’s electrical couplings.

Originally due to come on stream in 2017 and with an estimated 300 million barrels of recoverable reserves, the 4.5 billion pound ($5.9 billion) project has been plagued by delays.

The latest, pushing the expected launch back from the first to the second half of this year, follows a decision taken in November by Norwegian operator Equinor to inspect all of Mariner’s 40,000 couplings.

Initial tests showed the couplings’ failure rate was too high, Equinor’s vice president for major projects, Morten Ruth, told Reuters on Wednesday.

“They (electrical couplings) can lead to an explosion if gas gets to the platform,” he said. As of this week the company had completed 56 percent of the work.

“We see the startup getting closer. We see that we will be able to complete all preparations before July, but there are uncertainties,” he said, adding that he now expected the start-up between July and the beginning of September.

Ruth declined to say what extra costs the delay would entail.

The North Sea field, discovered east of the Shetland Islands in 1981, was approved for development in 2012.

Mariner is expected to produce around 55,000 barrels per day at plateau. That compares with current UK production of around 1.2 million bpd, according to International Energy Authority data.

Equinor has a 65.11 percent stake in the project. Its partners are JX Nippon with 20 percent, Siccar Point with 8.89 percent and Dyas with 6 percent.

The platform’s topside was built at a Daewoo Shipbuilding & Marine Engineering (DSME) yard in South Korea.

Mariner has been hit by several delays, and Equinor last October abandoned plans for a late 2018 production start.

Accommodation rig provider Prosafe said in a statement that Equinor had extended the lease of one of its service vessels for work at Mariner by three months until the end of September at a cost of $15 million.

($1 = 0.7651 pounds) (Additional reporting by Alex Lawler in London; Editing by Terje Solsvik and John Stonestreet)

(c) Copyright Thomson Reuters 2019.

Unlock Exclusive Insights Today!

Join the gCaptain Club for curated content, insider opinions, and vibrant community discussions.

Sign Up
Back to Main
polygon icon polygon icon

Why Join the gCaptain Club?

Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.

Sign Up
close

JOIN OUR CREW

Maritime and offshore news trusted by our 110,264 members delivered daily straight to your inbox.