Ships transit the Panama Canal’s new Agua Clara locks, located on the Atlantic side of the waterway. Photo: Panama Canal Authority
PANAMA CITY, July 31 (Reuters) – The head of the Panama Canal Authority said on Monday a Miami-based arbitration board rejected a demand by Spanish-led GUPC consortium for $192.8 million to cover cost overruns during the building of a third set of locks for the century-old waterway.
GUPC or Grupo Unidos por el Canal includes Sacyr SA of Spain, Impregilo of Italy, Jan De Nul of Belgium and Constructura Urbana of Panama.
The authority’s chief executive, Jorge Quijano, announced the ruling in a post on his Facebook page.
“We have been informed that we have won a major arbitration dealing with the expansion of the canal by the GUPC contractor for $192.8 million,” Quijano wrote in a post.
A spokesperson for the Panama Canal Authority (ACP) said it was not authorized to provide a copy of the ruling, and the arbitration tribunal with the Miami-based International Chamber of Commerce did not respond to a request for the ruling.
A local public relations firm that works with GUPC said that the consortium had no immediate comment.
The GUPC consortium’s request for a delay in the case and its demand for $192.8 million from the canal authority were both rejected by the arbitration panel, the authority said in a statement.
The consortium that had argued the canal authority should compensate it for costs associated with temporary water infrastructure it built on the Pacific entrance of the canal.
The canal authority said in the statement the arbitration panel has ordered GUPC to pay more than $22 million for the authority’s expenses associated with the arbitration, as well as $900,000 in additional reimbursements.
The $5.4 billion expansion of the Panama Canal was completed in June 2016. (Reporting by Elida Moreno; Writing by David Alire Garcia; Editing by Cynthia Osterman)
COPENHAGEN, April 15 (Reuters) – Shipping company Maersk has not made any deployment changes after a Portuguese-flagged container ship was seized by Iran in the Strait of Hormuz on Saturday, the Danish company said on Monday. “We find recent...
WASHINGTON, April 15 (Reuters) – The FBI has opened a federal criminal investigation into the deadly collapse of a Baltimore bridge last month when a ship crashed into one of its supports,...
By Daryna Krasnolutska (Bloomberg) Russia and Ukraine may have struggled to shift things significantly on the battlefield for more than 16 months, but a new phase of the war is moving...
April 14, 2024
Total Views: 2116
Why Join the gCaptain Club?
Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.