PANAMA CITY (Reuters) – A dispute resolution board dismissed a $100 million complaint for cost overruns by the consortium that built the third set of Panama Canal locks, part of a $5.4 billion expansion completed in June, the waterway authority said on Friday.
The Panama Canal Authority said in a statement that the board rejected a complaint last month asking the authority to cover cost overruns by Grupo Unidos Por el Canal (GUPC), a consortium led by Spain’s Sacyr and Italy’s Impregilo .
The board is comprised of members of the Panama Canal Authority and the consortium.
The complaint was presented by the consortium for “unforeseeable physical conditions” which it said contributed to more than $3.5 billion in cost overruns.
The consortium will likely appeal the decision with an international court of arbitration in Miami.
A representative of GUPC in Panama could not be immediately reached for comment. (Reporting by Elida Moreno; Writing by Natalie Schachar; editing by Grant McCool)
ROME (Reuters) – An Italian judge on Friday cleared three migrant sea rescue charities that had been accused of abetting irregular immigration in complicity with human traffickers, throwing out a case opened...
(Bloomberg) — The closure of one of the East Coast’s busiest ports after the collapse of Baltimore’s Francis Scott Key Bridge has so far not led to broad price increases,...
(Bloomberg) — An Iranian ship that’s been linked to Houthi attacks in the Red Sea is returning home, removing a prominent asset in the area as the Islamic Republic braces...
April 18, 2024
Total Views: 1489
Why Join the gCaptain Club?
Access exclusive insights, engage in vibrant discussions, and gain perspectives from our CEO.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.