    Default The Drilling Safety Rule

    The "BOEM will accept and consider public comments submitted within 60 days of the rule’s publication". Please read the "Drilling Safety Rule" in it's entirety HERE, and voice your opinion....
    Last edited by Mikey; September 30th, 2010 at 04:24 PM.
    Share on Facebook

  2. #2
    admin is offline Administrator
    Join Date
    Jun 2007
    Posts
    304
    Thanks
    1
    Thanked 9 Times in 5 Posts

    Default Re: The Drilling Safety Rule

    THE BUREAU OF OCEAN ENERGY MANAGEMENT,
    REGULATION AND ENFORCEMENT
    Office of Public Affairs
    FACT SHEET

    THE DRILLING SAFETY RULE
    An Interim Final Rule to Enhance Safety Measures for Energy
    Development on the Outer Continental Shelf

    The Bureau of Ocean Energy Management, Regulation and Enforcement (BOEM) is submitting to the Federal Register for publication the interim final Drilling Safety Rule. The Drilling Safety Rule will be effective immediately upon publication.

    The Drilling Safety Rule imposes requirements that will enhance the safety of oil and gas drilling operations on the Outer Continental Shelf (OCS). It addresses both well bore integrity and well control equipment and procedures.

    Well bore integrity provides the first line of defense against a blowout by preventing a loss of well control. It includes the appropriate use of drilling fluids and the well bore casing and cementing program. Provisions in the rule addressing well bore integrity are:

    • Making mandatory the currently voluntary practices recommended in the American Petroleum Institute’s (API) standard, RP 65 – Part 2, Isolating Potential
    • Flow Zones During Well Construction (an industry standard program)
    • Requiring submittal of certification by a professional engineer that the casing and cementing program is appropriate for the purposes for which it is intended under expected wellbore pressure
    • Requiring two independent test barriers across each flow path during well completion activities (certified by a professional engineer)
    • Ensuring proper installation, sealing and locking of the casing or liner
    • Requiring approval from the BOEM District Manager before replacing a heavier drilling fluid with a lighter fluid
    • Requiring enhanced deepwater well control training for rig personnel.

    Well control equipment includes the Blowout Preventer (BOP) and control systems that activate the BOP. Provisions in the rule on well control equipment include:

    • Submittal of documentation and schematics for all control systems
    • Requirements for independent third party verification that the blind-shear rams are capable of cutting any drill pipe in the hole under maximum anticipated surface pressure
    • Requirement for a subsea BOP stack equipped with Remotely Operated Vehicle (ROV) intervention capability (at a minimum the ROV must be capable of closing one set of pipe rams, closing one set of blind-shear rams, and unlatching the Lower Marine Riser Package)
    • Requirement for maintaining a ROV and having a trained ROV crew on each floating drilling rig on a continuous basis
    • Requirement for auto shear and deadman systems for dynamically positioned rigs
    • Establishment of minimum requirements for personnel authorized to operate critical BOP equipment
    • Requirement for documentation of subsea BOP inspections and maintenance according to API RP 53, Recommended Practices for Blowout Prevention Equipment Systems for Drilling Wells
    • Require testing of all ROV intervention functions on subsea BOP stack during stump test and testing at least one set of rams in initial seafloor test
    • Require function testing auto shear and deadman systems on the subsea BOP stack during the stump test and testing the deadman system during the initial test on the seafloor
    • Require pressure testing if any shear rams are used in an emergency.

    This Drilling Safety Rule is issued under an emergency rulemaking process consistent with Administrative Procedure Act (APA) requirements. The equipment, systems and improved practices stipulated in the rule are immediately necessary for the safety of OCS oil and gas drilling operations and the protection of the environment.

    While the rule is effective immediately upon publication, BOEM will accept and consider public comments submitted within 60 days of the rule’s publication. The agency will then either publish a new rule with modifications in light of comments received or publish a notice that will confirm the rule as final with no additional changes.

    This rule is based upon recommendations contained in Secretary Salazar’s May 27th, 2010, Safety Measures Report to the President and codifies ongoing requirements of Notice to Lessees No. 2010-N05 (NTL 5).
    BOEM intends to address additional provisions considered appropriate in light of the Deepwater Horizon explosion in additional rulemakings in the coming months.
    Share on Facebook

Similar Threads

  1. Delays in Drilling Even After Deep Water Drilling Ban is Lifted
    By Jones Act in forum Maritime Law News
    Replies: 2
    Last Post: January 3rd, 2011, 03:49 PM
  2. 3 watch rule
    By Azimuth in forum Tugs & Towing
    Replies: 2
    Last Post: December 9th, 2010, 06:52 PM
  3. NPRM STCW Proposed Rule QSS Requirement
    By bardawg48 in forum Maritime Training & Licensing
    Replies: 2
    Last Post: December 15th, 2009, 03:18 AM
  4. Proposed Rule Implementation of 1995 Amendments to STCW
    By jdcavo in forum Maritime Training & Licensing
    Replies: 3
    Last Post: November 17th, 2009, 02:44 AM
  5. USCG 90-day rule for applications
    By john in forum Professional Mariner Forum
    Replies: 0
    Last Post: April 15th, 2008, 04:09 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  

Content Relevant URLs by vBSEO 3.6.0 PL2