Results 1 to 15 of 15

Thread: D.P. Dredges

  1. #1
    CoastalDPO is offline gCaptain Crew Greenhorn
    Join Date
    Jun 2011
    Posts
    70
    Thanks
    0
    Thanked 5 Times in 5 Posts

    Default D.P. Dredges

    Does anyone know of any compainies on on the East Coast of the U.S. that operates D.P. dredges?
    Share on Facebook

  2. #2
    mtskier's Avatar
    mtskier is offline Old Salt
    Join Date
    Nov 2007
    Location
    48.45N 114.5W Elevation 3250
    Posts
    472
    Thanks
    138
    Thanked 46 Times in 33 Posts

    Default

    Or west coast for that matter.
    Share on Facebook

  3. #3
    gatorzeroone is offline gCaptain Crew
    Join Date
    Mar 2012
    Posts
    43
    Thanks
    13
    Thanked 4 Times in 4 Posts

    Default Re: D.P. Dredges

    I have been looking into the dredging industry, and I dont think DP is used for dredging. From what I have seen the suction cutters use anchor and spud to move the dredge during operations and tug for location movements. I was wondering how the anchors are set; with a tug I assume. I'm not sure but the hopper type dredge is a ship with bow thrusters, but I'm not sure is that counts a DP. Anyone else care to give a better answer; I would be interested in knowing the real answer from a dredging professional. Dredging seems to be a booming industry right now. I am trying to get on as a field engineer with a dredging outfit. There are some great youtube vids for dredging.
    Share on Facebook

  4. #4
    PR-9's Avatar
    PR-9 is online now Old Salt
    Join Date
    Jul 2011
    Location
    Texas
    Posts
    376
    Thanks
    31
    Thanked 45 Times in 34 Posts

    Default

    I don't think any US Hopper Dredges have DP. But I seen foreign ones that do. They have incorporated the survey info with a DP 1 type system. Marine Log had an article about a new built for A foreign company.
    Share on Facebook

  5. #5
    dredgeboater's Avatar
    dredgeboater is online now Old Salt
    Join Date
    Jan 2010
    Location
    San Francisco Bay Area
    Posts
    224
    Thanks
    54
    Thanked 58 Times in 37 Posts

    Default

    I am pretty sure Manson Construction Company's hopper dredge Glenn Edwards has a DP System. That is probably the only US Flag hopper dredge that is outfitted with a DP system though. DP would work great on hopper dredges, particularly for disposal operations, but most of the US Flag hopper dredges are 30+ years old and not going to be outfitted with DP. Weeks Marine is currently building a new US Flag hopper dredge to an IHC design and I don't know if it will be DP or not. Many foreign flag hopper dredges have class noted DP systems.
    Share on Facebook

  6. #6
    Wolfesown47th is online now gCaptain Crew
    Join Date
    Mar 2012
    Location
    Detroit
    Posts
    39
    Thanks
    4
    Thanked 22 Times in 15 Posts

    Default Re: D.P. Dredges

    I've never heard of a double penetration dredge. ;-)
    Share on Facebook

  7. The Following User Says Thank You to Wolfesown47th For This Useful Post:

    SSG33 (September 19th, 2012)

  8. #7
    Fraqrat's Avatar
    Fraqrat is online now Top Contributer
    Join Date
    Mar 2011
    Location
    Alabama
    Posts
    1,079
    Thanks
    659
    Thanked 815 Times in 383 Posts

    Default

    Quote Originally Posted by Wolfesown47th
    I've never heard of a double penetration dredge. ;-)
    It's probably some new contraption being built by Gary Chouest to take over the dredge business.... Hey wait a minute...
    Share on Facebook

  9. #8
    dirwood is offline gCaptain Crew
    Join Date
    Feb 2008
    Posts
    22
    Thanks
    1
    Thanked 7 Times in 4 Posts

    Default Re: D.P. Dredges

    Quote Originally Posted by dredgeboater View Post
    I am pretty sure Manson Construction Company's hopper dredge Glenn Edwards has a DP System. That is probably the only US Flag hopper dredge that is outfitted with a DP system though. DP would work great on hopper dredges, particularly for disposal operations, but most of the US Flag hopper dredges are 30+ years old and not going to be outfitted with DP. Weeks Marine is currently building a new US Flag hopper dredge to an IHC design and I don't know if it will be DP or not. Many foreign flag hopper dredges have class noted DP systems.
    The Glenn Edwards is outfitted with a Kongsberg DP system and it has has worked exceptionaly well since its installation.
    Share on Facebook

  10. #9
    mtskier's Avatar
    mtskier is offline Old Salt
    Join Date
    Nov 2007
    Location
    48.45N 114.5W Elevation 3250
    Posts
    472
    Thanks
    138
    Thanked 46 Times in 33 Posts

    Default

    I was curious because we work in DP Track constantly running a route. It seems like a very efficient way to consistently cut material and cover a prescribed area.
    Share on Facebook

  11. #10
    george44 is online now gCaptain Crew
    Join Date
    Apr 2009
    Posts
    84
    Thanks
    9
    Thanked 11 Times in 10 Posts

    Default

    Quote Originally Posted by dredgeboater
    I am pretty sure Manson Construction Company's hopper dredge Glenn Edwards has a DP System. That is probably the only US Flag hopper dredge that is outfitted with a DP system though. DP would work great on hopper dredges, particularly for disposal operations, but most of the US Flag hopper dredges are 30+ years old and not going to be outfitted with DP. Weeks Marine is currently building a new US Flag hopper dredge to an IHC design and I don't know if it will be DP or not. Many foreign flag hopper dredges have class noted DP systems.
    It won't be, DP that is. It's not gonna be out til 2014 sometime.
    The Glenn Edwards does have DP and we envy them for it.
    Outta curiosity, how's the pay for mates and abs at Manson?
    Share on Facebook

  12. #11
    dredgeboater's Avatar
    dredgeboater is online now Old Salt
    Join Date
    Jan 2010
    Location
    San Francisco Bay Area
    Posts
    224
    Thanks
    54
    Thanked 58 Times in 37 Posts

    Default

    Quote Originally Posted by george44

    It won't be, DP that is. It's not gonna be out til 2014 sometime.
    The Glenn Edwards does have DP and we envy them for it.
    Outta curiosity, how's the pay for mates and abs at Manson?
    They are the top paying company in the US hopper dredging industry. I am not sure of exact numbers but I believe it is close to the top paying OSV companies, particularly if you factor in getting paid your full day rate for travel days. Good luck getting on as a mate or AB though. There is near zero turnover deck side. I know they have openings for engineers every now and then. Do you work at Weeks?
    Share on Facebook

  13. #12
    kfj
    kfj is offline Old Salt
    Join Date
    Aug 2009
    Location
    South East
    Posts
    393
    Thanks
    30
    Thanked 41 Times in 31 Posts

    Default Re: D.P. Dredges

    I flew with a manager in the dredge division at Manson and he told me the crews vote for the new hires and my chances of getting hired were slim to none unless I knew someone on one
    Share on Facebook

  14. #13
    george44 is online now gCaptain Crew
    Join Date
    Apr 2009
    Posts
    84
    Thanks
    9
    Thanked 11 Times in 10 Posts

    Default

    Yup. Been on a few hitches...

    The new boat is gonna require 3 mates, whichll be nice; currently the 6 and 6 is pretty brutal on a quick turnaround job. 8-10 loads a day so...
    Share on Facebook

  15. #14
    dredgeboater's Avatar
    dredgeboater is online now Old Salt
    Join Date
    Jan 2010
    Location
    San Francisco Bay Area
    Posts
    224
    Thanks
    54
    Thanked 58 Times in 37 Posts

    Default

    Quote Originally Posted by george44
    Yup. Been on a few hitches...

    The new boat is gonna require 3 mates, whichll be nice; currently the 6 and 6 is pretty brutal on a quick turnaround job. 8-10 loads a day so...
    Good for the day and a half per day seatime, bad for sleep. Did a production job in Greys Harbor, WA where the disposal site was right next to the cut and the sand just jumped in the hopper. That was about 20 loads a day or so. I would be surprised if the USCG required more than 2 mates for dredging ops beyond the initial proving period. If they do, all I have to say is about time.
    Share on Facebook

  16. #15
    george44 is online now gCaptain Crew
    Join Date
    Apr 2009
    Posts
    84
    Thanks
    9
    Thanked 11 Times in 10 Posts

    Default

    The new one sounds like its guaranteed to have three mates from what's being said; it'll have lifeboats too, not just rafts.
    Share on Facebook

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  

Content Relevant URLs by vBSEO 3.6.0 PL2